NASA has terminated an ambitious mission intended to map ice and then drill into it at the Moon’s south pole. The space agency announced the cancellation of the Volatiles Investigating Polar Exploration Rover (VIPER) on 17 July, citing budget woes and several delays in the construction of the rover and its lander that have led to rising costs. Now, it is seeking partners interested in using the rover — which is already assembled — or components of it, for future lunar missions.
The agency has already sunk nearly US$450 million into building VIPER, and reports that it would need to spend millions more to complete testing. This would threaten funding for other launches it is planning as part of its Commercial Lunar Payload Services (CLPS) programme, in which the agency works with private US aerospace companies to transport scientific instruments to the lunar surface. Before the mission delays, VIPER was intended to be the first-ever mission to scout for ice on the ground at the Moon’s south pole.
“This has been a really tough decision, which we make in an uncertain budget environment,” said Nicola Fox, associate administrator for NASA’s science mission directorate in Washington DC, when announcing the cancellation. “But we do believe that this is a way for us to continue to support the entire CLPS portfolio.” The US Congress gave NASA a smaller budget for 2024 than it did in 2023, and the budget proposed for 2025 by the US House of Representatives is only about a 1% increase from this year, which is lower than the current US rate of inflation.
Delayed, then doomed
The US Congress approved $433.5 million to be spent building VIPER and landing it on the Moon by the end of 2023. The idea was to sample ice in the dark, cold craters at the lunar south pole, with the aim of extracting the chemical data trapped inside it, to learn more about the origin and formation of the Solar System. The ice could also serve as a rocket-fuel ingredient for future lunar astronauts. But delays in building the rover and the commercial lander that would deliver it to the Moon pushed the launch date to late 2025, with an estimated cost rise of $176 million, according to Joel Kearns, the deputy associate administrator for exploration at NASA’s science mission directorate. The cost spike triggered an internal agency review, which was completed in June.
…
Photo of VIPER courtesy of NASA.